GOVERNMENT OF INDIA
Ministry of Urban Development
RAJYA SABHA
UNSTARRED QUESTION NO. 2783
ANSWERED ON MARCH 21, 2013
QUESTION
Storm Drain Projects under JNNRUM
2783. SHRI RAJEEV CHANDRASEKHAR:
Will the Minister of URBAN DEVELOPMENT be pleased to state:
(a) Whether it is a fact that work on storm drain projects sanctioned under Jawaharlal Nehru National Urban Renewal Mission (JNNURM) in Bangalore are yet to commence, or have been delayed;
(b) if so, the reasons therefor;
(c) the details of such projects with dates on when these were sanctioned and their current status; and
(d) the steps Government has taken or proposes to take to address this issue?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF URBAN DEVELOPMENT
(SMT. DEEPA DASMUNSHI)
(a) & (b): Four projects of Remodelling of Storm Water Drains (SWD) in Challaghatta, Vrushabhavathi, Hebbal and Koramangala valleys in Bangalore were taken up under Urban Infrastructure & Governance (UIG) Sub-Mission of Jawaharlal Nehru National Urban Renewal Mission (JnNURM) by the Government of Karnataka. Works have been delayed and stopped due to non-availability of work fronts and poor performance of contractors.
(c): The Detailed Project Reports (DPRs) for the four projects was originally approved by the Government of India (GoI) for funding under UIG Sub-Mission of JnNURM on 24.11.2006. The details and the current status of the four projects is annexed.
(d): It has been intimated by the Government of Karnataka (GoK) that the State Level Empowered Committee chaired by the Chief Secretary, GoK, in its 21st Meeting held on 11.01.2012, has constituted a Committee headed by the Additional Chief Secretary, GoK to monitor the progress of the projects and frame a Work Plan for implementation of the projects.
Annexure
Amount Rs. in lakh
Date as on 15-3-2013
PROJECT IMPLEMENTATION STATUS OF FOUR PROJECTS OF BANGALORE
Sl. No. |
Project Title |
Approved Cost |
Date of CSMC/CCEA/ CCI Meeting/ Project Approval |
Total ACA Commitment (Central Share) |
Date of Last ACA Released |
Installment Numbers |
As per MoF Release-Order ACA Released till date |
Utilisation as per Dec’12 QPR |
% of Amount Utilised against Approved Cost |
% of Work Completed (Physical Progress) |
Date of Completion as per latest QPR |
1 |
Remodelling of Primary and Secondary storm water draw-in in Bangalore city at Vrushabhavathi valley including Kethamaranahalli and arkavathi minor valley I and Kathriguppa minor valley III (3 DPRs) |
42,089.00 |
24-Nov-06 |
7,989.10 |
22-May-09 |
3 |
5,991.81 |
19,790.00 |
47% |
57% |
Mar-14 |
2 |
Remodelling of Primary and Secondary storm water drains in Bangalore City Challaghatta valley |
10,593.00 |
24-Nov-06 |
3,337.25 |
8-Feb-08 |
2 |
2,074.96 |
5,082.31 |
48% |
35% |
Mar-14 |
3 |
Remodelling of Primary and Secondary storm water draw-in Bangalore city, Koramangala valley |
12,858.00 |
24-Nov-06 |
3,902.15 |
9-Sep-09 |
3 |
2,926.59 |
8,376.09 |
65% |
54% |
Mar-14 |
4 |
Remodelling of Primary and secondary storm water drains in Bangalore city, Hebbal valley |
26,998.00 |
24-Nov-06 |
6,465.90 |
9-Sep-09 |
3 |
4,849.41 |
12,474.82 |
46% |
35% |
Mar-14 |
Total |
92,538.00 |
|
21,694.40 |
|
|
15,842.77 |
|
49% |
|
|