GOVERNMENT OF INDIA |
Ministry of Finance
|
DEPARTMENT OF ECONOMIC AFFAIRS |
RAJYA SABHA |
UNSTARRED QUESTION NO 1554 |
TO BE ANSWERED ON 08.08.2006 |
Private Public Partnership Financing of Infrastructure Projects |
1554. |
SHRI RAJEEV CHANDRASEKHAR |
|
|
Will the Minister of FINANCE be pleased to state:-
(a)what is the total cumulative net quantum of FDI (excluding FII) into various Infrastructure projects since May, 2004;
(b)what is the status of the private-Public partnership financing of infrastructure projects;
(c)if so, how many projects have been approved under this programme;
(d)what is the total quantum involved and the details of these projects; and
(e)how many projects under private-public partnership are being considered for financing from Karnataka?
ANSWER
Minister of State in the Ministry of Finance
( SHRI PAWAN KUMAR BANSAL)
(a) Sector-wise FDI inflows during 2004 (January - December), 2005 (January - December) and 2006 (January - March) including that of infrastructure sectors, is given at Annex-I,
(b) to (e): For those Public Private Partnership projects in infrastructure sector, which are commercially not viable but have a high economic value, the Government of India had announced the scheme of Viability Gap Funding (VGF) in August, 2005. The scheme covers only those PPP projects in the infrastructure sector, which are to be implemented by a private entity that is selected through a competitive and transparent bidding process. The status of the proposals received so far under this scheme is at Annex-II.
Annex – I
(Amount in Rs. Million)
SL NO
|
Sector |
2004 (Jan-Dec) |
2005 (Jan – Dec) |
2006 (Jan-Mar) |
1 |
Electrical equipment (INCL S/W & ELEC) |
39666.61 |
45938.44 |
27030.64 |
2 |
TELECOMMUNICATIONS |
6087.84 |
9639.13 |
21374.32 |
3 |
TRANSPORTATION INDUSTRY |
8063.68 |
9659.22 |
1530.99 |
4 |
SERVICE SECTOR |
11455.83 |
31445.14 |
5298.97 |
5 |
FUELS (POWER & OIL REFINERY) |
7159.79 |
2765.05 |
2656.75 |
6 |
CHEMICALS (OTHER THAN FERTILISERS) |
8677.14 |
9044.68 |
11234.01 |
7 |
FOOD PROCESSING INDUSTRIES |
3690.18 |
1782.91 |
244.79 |
8 |
DRUGS & PHARMACEUTICALS |
15711.08 |
5107.25 |
2608.94 |
9 |
CEMENT AND GYPSUM PRODUCTS |
7.3 |
19698.17 |
0 |
10 |
METALLURGICAL INDUSTRIES |
8583.79 |
6321.99 |
1211.69 |
11 |
CONSULTANCY SERVICES |
11843.5 |
1627.16 |
679.15 |
12 |
MISCELLANEOUS MECHANICAL & ENGINEERING |
717.26 |
2224.73 |
42.43 |
13 |
TEXTILES (INCLUDE DYED,PRINTED) |
1784.77 |
3462.16 |
884.65 |
14 |
TRADING |
682.16 |
1257.67 |
213.98 |
15 |
PAPER AND PULP INCLUDING PAPER PRODUCT |
175.55 |
1229.04 |
0 |
16 |
HOTEL & TOURISM |
1527.23 |
2799.59 |
642.74 |
17 |
GLASS |
384.74 |
32.72 |
2.7 |
18 |
RUBBER GOODS |
2012.55 |
1516.41 |
13.35 |
19 |
INDUSTRIAL MACHINERY |
430.76 |
1474.73 |
430.43 |
20 |
COMMERCIAL, OFFICE & HOUSEHOLD EQUIPMENT |
108.16 |
1556.95 |
73.92 |
21 |
AGRICULTURAL MACHINERY |
0 |
2777.52 |
1382.28 |
22 |
MACHINE TOOLS |
2652.7 |
1001.11 |
11.41 |
23 |
TIMBER PRODUCTS |
0.67 |
4658.77 |
0.1 |
24 |
MEDICAL AND SURGICAL APPLIANCES |
229.27 |
72.62 |
10.69 |
25 |
SOAPS, COSMETICS AND TOILET PREPARATIONS |
40.95 |
3829.82 |
55.05 |
26 |
CERAMICS |
1208.24 |
276.42 |
0 |
27 |
EARTH-MOVING MACHINERY |
5.22 |
2313 |
0 |
28 |
FERTILIZERS |
620 |
193.13 |
0 |
29 |
FERMENTATION INDUSTRIES |
339.37 |
362.8 |
0 |
30 |
LEATHER, LEATHER GOODS AND PICKERS |
20.36 |
42.79 |
6.09 |
31 |
VEGETABLE OILS AND VANASPATI |
271.38 |
601.66 |
99.66 |
32 |
GLUE AND GELATIN |
0 |
0 |
0 |
33 |
PRIME MOVERS OTHER THAN ELECTRICALS |
2.49 |
0 |
0 |
34 |
INDUSTRIAL INSTRUMENTS |
49.45 |
1.17 |
15.77 |
35 |
SUGAR |
135.09 |
131.04 |
0 |
36 |
SCIENTIFIC INSTRUMENTS |
1.37 |
4.5 |
0 |
37 |
PHOTOGRAPHIC RAW FILM AND PLANTS |
12.75 |
264.33 |
0 |
38 |
DYE-STUFFS |
54.2 |
0 |
0 |
39 |
BOILERS AND STEAM GENERATING PLANTS |
0 |
23.4 |
0 |
40 |
DEFENCE INDUSTRIES |
0 |
2.37 |
0 |
41 |
MATHEMATICAL, SURVEYING AND DRAWING |
0 |
0 |
0 |
42 |
MISCELLANEOUS INDUSTRIES |
13400.28 |
17567.6 |
4435.56 |
43 |
Acquisition of Shares |
0 |
0 |
0 |
44 |
Advance of Inflow |
24851.48 |
0 |
0 |
45 |
Stock Swapped |
0 |
283.71 |
0 |
46 |
NRI-RBI Schemes |
0 |
0 |
0 |
|
Grand Total |
172665.2 |
192990.9 |
82191.07 |
Note: 1. Amount includes the Inflows Received through SIA/FIPB route acquisition of existing shares and RBI’s automatic route only.
Annex - II
Status of the Proposals received under the Scheme of Viability Gap Funding
(As on 31.07.2006)
S.NO |
Name of the project & State |
Project cost (Rs. Cr.) |
VGF Sought (Rs. Cr.) |
Status |
|
Proposal given final approval |
|
|
|
|
NIL |
|
|
|
|
Proposal given in-principle approval |
|||
1. |
Four laning of Ahmedabad Viramgam Road, Gujrat |
166.68 |
33.34 |
In-principle approval granted by the Empowered Institution on 17.2.2006. Project Authority has been given two month extension for seeking bids. |
2. |
Four laning of Rajkot-Jamnagar-Vadinagar. Gujarat |
543.21 |
108.64 |
In-principle approval granted by the Empowered Institution on 17.2.2006. Project Authority has been given two month extension for seeking bids. |
3. |
Halol- Godhara- Shamalaj I Road Gujrat, |
498.81 |
99.76 |
In-principle approval granted by the Empowered Institution on 17.2.2006. Project Authority has been given two month extension for seeking bids. |
4. |
Four laning of Osmanabad (Yedshi)-Lathur-Nanded Road, Maharashtra. |
300.19 |
60 |
In-principle approval granted by the Empowered Institution on 17.3.2006. |
5. |
Nashik-Aurangabad road SH-30 section Nashik Nipad Yeola Vaijapur, Maharashtra. |
157.50 |
31.50 |
In-principle approval granted by the Empowered Institution on 17.3.2006. |
6. |
Strengthening of Mandsaur-Sitamau Road (upto Rajasthan Border), Rajasthan. |
21.99 |
4.398 |
In-principle approval granted by the Empowered Institution on 22.6.2006. |
7. |
Matkuli-Taia-Chindwara. Rajasthan. |
82.19 |
16.438 |
In-principle approval granted by the Empowered Institution on 22.6.2006. |
8. |
Chandapur-Alirajpur-Kukshi-Badwani State Highways in Madhyapradesh, Rajasthan. |
47.53 |
9.506 |
In-principle approval granted by the Empowered Institution on 22.6.2006.
|
9. |
Upgradation of Sawai-Madhopur to Bharatpur State Highway, Rajasthan, Rajasthan. |
244.38 |
48.80 |
In-principle approval granted by the Empowered Institution on 22.6.2006. |
10. |
Upgradation of Jaipur to Nagpur State Highway, Rajasthan, Rajasthan. |
220 |
44 |
In-principle approval granted by the Empowered Institution on 22.6.2006. |
11. |
Upgradation of Jaipur to Bhilwara State Highway, Rajasthan, Rajasthan. |
247 |
49.40 |
In-principle approval granted by the Empowered Institution on 22.6.2006. |
12. |
Upgradation of Bhilwara to Bundi State Highway, Rajasthan. |
120 |
24 |
In-principle approval granted by the Empowered Institution on 22.6.2006. |
|
Sub-Total |
2649.48 |
529.782 |
|
|
Proposal yet to be considered by Empowered Institution |
|||
13 |
Upgradation of Narnaul to Kotpulti-Chala-Sikar-Khud-Losal-Kuchaman State Highway, Rajasthan. |
193 |
38.60 |
Document circulated on 1.6.06.
|
14 |
Development of two lane carriageway to Dabadeh to Bhawan Mandi. Rajasthan. |
63 |
12.60 |
Document circulated on 14.6.06 |
15. |
Two Lane Carriage for Jobner to Thanagaji-Reg. VGF Rajasthan. |
171 |
34.20 |
To be circulated |
|
Sub-Total |
427 |
85.40 |
|
Proposals with outstanding Issues |
||||
16. |
Mumbai Metro Rail Project-Implementation of Vesova-Andheri-Ghatkopar corridor Maharashtra. |
2356 |
650 |
Additional information has been sought from Project Authority. |
17 |
Upgradation of 8 State Highways in Punjab, Punjab. |
564.30 |
112.86 |
Document circulated. DPR have been sought from PIDB. |
18. |
Turial Hydro Electric Project (60 MW) in Mizoram- Ministry of Power Mizoram, |
687.80 |
152 |
Incomplete report received-MOP. Reply still awaited. |
19. |
Integerated waste processing complex at NDMC Compost Plant, Okhla. Delhi. |
82.30 |
16.46 |
The proposal does not meet some of the conditions.
|
20. |
Transmission Project in Tripura, Tripura. |
1625 |
325.00 |
The proposal does not meet some of the conditions. Additional information sought from project Authority. |
21. |
Integerated Muncipal Waste Processing Complex at Okhla (MCD) Delhi. |
49.44 |
9.88 |
The proposal does not meet some of the conditions. Proposal is being examined further in consultation with MNES. |
22. |
Garbage Processing plant at Timarpur Delhi. |
55.5 |
11.12 |
The proposal does not meet some of the conditions Proposal is being examined further in consultation with MNES. |
23. |
Development of Deep water International container Transhipment Terminal at Vizhinjam, Kerala. |
4360 |
198.47 |
The proposal does not meet some of the conditions. Proposal is being examined. |
|
Sub-Total |
9780.34 |
1475.79 |
|
|
Proposals Rejected |
|
|
|
24. |
Integerated Waste to Energy Project between Bangalore Mahanagara Palike and M/s Srinivasa Gayithri Resources Recovery Ltd. Karnataka. |
11.72 |
2.34 |
Proposal has been rejected as it did not conform to the VGF Scheme |
25. |
Four-laning of the existing two lane Sardar Patel Ring Road around Ahmedabad city Gujrat. |
378.75 |
75.75 |
Proposal not accepted in its present form. Project Authority requested to re-submit with changes. |
|
Sub-Total |
390.47 |
78.09 |
|
|
Grand Total |
13247.29 |
2169.062 |
|